====== Town planning: redesigning the sector around the station of La Verpillière ======
{{:start:1-france:b-redesigning:architecture:architecture.jpg?200 |}} After having met with the town's mayor and elected representatives responsible for urban planning and economic development, students were left with a number of parameters to bear in mind. And students were also given a time frame to come up with a solution for the redevelopment of the sector around the station that they would need to present to La Verpillière Town Council in May 2015.
[[start:1-france:b-redesigning|Back]]
====== Needs and constraints linked to redeveloping the station of La Verpillière ======
===== Needs and issues at stake=====
- Getting rid of the level crossing,
- re-routing traffic from the D126 road to avoid unnecessary traffic congestion,
- developing the station for the projected increase in passenger traffic,
- re-working the traffic flows along the Avenue de la Gare,
- re-siting the Sainte-Marie Lyon school bus terminus,
- extending station car parking, but to what level?,
- improving safety around the station through reduced traffic flow,
- improving station access, as well as making crossing to the opposite platform easier,
- extending other sorts of parking (such as for bicycles and electric cars),
- favouring soft transport methods, especially between the station and the new outlet village,
- improving disabled access to and inside the station,
- creating a new bus terminus for public transport to and from the station,
- adding new services and/or shops for commuters,
- easing traffic flow.
===== Constraints-invariables =====
* All the stakeholders need to be in agreement.
* Making sure the La Verpillière-Villefontaine link road is maintained.
* Sainte-Marie Lyon school cannot be re-sited.
* The school gymnasium and other parts of the school are not open to the general public.
* Construction of a new outlet village is due to begin in early 2015, bringing increased traffic.
* The new housing development cannot be re-sited.
* Local businesses cannot be relocated.
* There is a habitat corridor for wildlife that cannot be built on.
* The site is relatively small and building potential limited.
====== Presentation by the French Town Hall ======
{{:start:1-france:b-redesigning:presentation_mairie_la_verpilliere_1-_sept_2014.jpg?800|}}
{{:start:1-france:b-redesigning:presentation_mairie_la_verpilliere_2_-_sept_2014.jpg?800|}}
{{:start:1-france:b-redesigning:aerial_view.jpg?460 |}}{{ :start:1-france:b-redesigning:aerial_view_2.jpg?490|}}
{{maplink:Gare LA VERPILLIERE:Google Maps - Site of La Verpillière's Station}}
===== Players =====
==== State ====
* Reginal and local authorities,
* La Verpillière Town Hall,
* Villefontaine Town Hall,
* North Isère Urban Authority (Communauté d’agglomération des Portes de l’Isère or "CAPI"),
* Isère Council,
* Rhone-Alps Regional Council,
* The French rail network provider: RFF.
==== Main private players ====
* The school Sainte-Marie Lyon,
* A company called Nemera.
===== Various solutions proposed and studied =====
* Getting rid of the level crossing.
* Re-routing the local road 1006 which goes over the level crossing.
* Creating an intermodal hub.
* Resiting of or safety improvement work on the Marist school bus park.
* Rethinking of the direction of traffic along Avenue Général de Gaulle and Avenue Général Giraud.
* Development of the Léman site.
* No resiting of the current La Verpillière station due to costs and political considerations.